top of page

Published on

17 Sept 2026

Delivering Oversized Process Equipment to Tuas South's Integrated Waste Management Facility

Aug 28
1 min read

Updated: Sep 18


Client: UES Holdings Pte Ltd
Sector: Environmental Infrastructure
Engagement: Q1–Q3 2025

The Challenge
UES Holdings needed to deliver and install a set of oversized process equipment — two 10m lime saturators, two 7m saturated lime holding tanks, and three 21m silos — at the Integrated Waste Management Facility (IWMF) in Tuas South. Road restrictions ruled out a straightforward land delivery for several of the units, and the client was weighing whether to assemble on site or import the equipment pre-built from China, a decision that carried real trade-offs between logistics complexity and on-site labour.

The Solution
Eng Lee managed the full last-mile delivery by sea and land, moving the equipment from Singapore port to the site's waterfront using a barge and tug combination, then discharging and installing it on site with a 700-ton mobile crane fitted with a 36m luffing jib, supported by a 250-ton crane to tilt the silos upright. Multi-axle trailers and auxiliary escorts handled road transport and internal repositioning of the oversized cargo.

The Outcome
By handling delivery and installation as a single coordinated scope, Eng Lee cut the manpower and time UES would otherwise have spent on site assembly — shaving roughly 50% off the projected timeline and letting production start earlier than planned.

By the Numbers
Metric

Value

Project duration

9 months

Fleet deployed

1x120ft barge, 2 tugboats, 700-ton crane, 250-ton crane, 3x multi-axle trailers

Items moved

7 oversized items, Singapore port to site

Routes covered

Marine & land

On-time performance

100%

Time savings

~50% vs. on-site assembly



bottom of page